An annual plan is not the list of requests received: it is the list of the ones you have the means to deliver. The difference rarely comes down to the budget, almost always to team capacity.

Every autumn, departments list their projects for the following year. Every spring, it turns out that half have not started. The plan was not bad: it was unrealistic from the start, for three recurring reasons.
The sixth step is often forgotten. Yet it prevents refused requests from coming back through the back door during the year.
A simple grid, applied to every request, is better than a sophisticated grid applied to a few.
| Criterion | Question | Example reading |
|---|---|---|
| Obligation | Is the project mandatory (regulatory, end of support, contract)? | Yes: it comes before the others, without scoring |
| Value | What gain, quantified or at least qualified? | Revenue, savings, risk avoided |
| Cost | How many days, of which skills, and how many euros? | An order of magnitude is enough at this stage |
| Risk | What technical, organisational or dependency uncertainty? | A high risk justifies a pilot work package |
| Alignment | Which strategic objective of the year does it serve? | None: it must be justified another way |
To then rank the qualified requests, see project prioritisation methods, with a worked example.
Everyone's roles in this qualification — who estimates, who decides, who is only informed — are worth writing down: see the RACI matrix.
The budget tells you whether you can pay. Capacity tells you whether you can deliver. An IT department can have the envelope it needs and still lack the three architects that every project needs in the second quarter.
The test is therefore done in two stages: first the sum of the estimates against the envelope, once the fixed part has been deducted (see building an IT department budget); then the sum of skill needs, month by month, against each team's available capacity (see capacity plan and capacity planning). It is almost always the second that forces the trade-offs.
The useful result is not "everything fits" or "nothing fits", but a list of scenarios: what holds if a given project is postponed by a quarter, if a given work package is subcontracted, if a given request is dropped.
An annual plan frozen in January is wrong by March. It must be reread every quarter, with the same rules as when it was built:
This discipline is what distinguishes an annual plan from a wish list.
See the Projects and Resources areas, and the IT departments page.
What this article describes is managed in these CESAR.TEAM modules.
Tell us how you manage today: structure, closing rhythm, systems in place. We will prepare a demo on a comparable context.