An IT budget is built in a few weeks and defended all year. The difficulty is not building it: it is holding together the committed part, which is not up for discussion, and the project part, which is discussed all the time.
An IT budget mixes two kinds of spending that don't obey the same rules.
Run — infrastructure, licences, support, maintenance, hardware renewal — is largely committed. It is forecast from previous years' actuals, plus known increases. It is only arbitrated at the margin, and cutting it sharply is paid for the following year.
Build — projects — is the only part that is really open to discussion. That is where alignment with strategy is decided, and where executive management expects well-argued trade-offs.
Presenting both in a single table invariably leads to the same dialogue: a request for a uniform cut of a few percent, applied to lines half of which cannot be compressed. Separating them changes the conversation.
The project share is managed as a portfolio: each project carries a budget, an in-house workload, a timeline and a priority. Three pitfalls come up systematically.
In-house days are not valued. A project delivered by the in-house team then appears free compared with a project entrusted to a contractor. Arbitration is based on a false comparison — and the in-house team ends up committed to three times its capacity.
Capacity is not compared with the plan. A portfolio approved without a capacity plan is a wish list. The question is not “can we fund these projects?” but “do we have the people to deliver them, in the months they are planned?”.
Change management is forgotten. Evolving an information system is a transformation project; the budget for training, support and data migration is not an adjustment variable.
A budget holds by how often it is compared with actuals. The minimum format, by item:
| Item | Planned | Committed | Actual | What to do with it |
|---|---|---|---|---|
| Infrastructure & cloud | yes | yes | yes | Track renewals and price increases |
| Licences | yes | yes | yes | Audit the number of seats actually used |
| External services | yes | yes | yes | The most volatile item: track committed, not invoiced |
| Projects | yes | yes | yes | Estimated cost at completion per project, not cumulative spend |
| Contingency | yes | — | yes | Tracked separately, otherwise it gets consumed without a decision |
The committed column is the one most often missing, and it is the one that prevents nasty surprises: for external services, the contractual commitment precedes the invoice by several months.