The breakdown chosen at estimating time determines everything you will be able to read afterwards. Breaking down by budget lines gives a budget finance can read. Breaking down by deliverables gives a budget comparable with production.
Estimating a project remains the most uncomfortable exercise in project management: you commit an amount on work that hasn't started. Three methods are used, and they are not mutually exclusive.
| Method | Principle | Accuracy | When to use it |
|---|---|---|---|
| Expert estimate | The project manager estimates by analogy with comparable deals | ± 20% | Pre-sales, order of magnitude, go/no-go |
| Analytical estimate | Breakdown of every cost item, resource by resource and supplier by supplier | ± 5 to 10% | Projects with strong contractual commitments |
| Estimate by deliverables | Breakdown of the project into deliverables, each estimated in skills then in actual resources | ± 10% | The common case: the best effort-to-accuracy ratio |
An expert estimate gives a figure in an hour and a margin of error you accept. An analytical estimate gives real accuracy, at the cost of work few teams sustain over time. Estimating by deliverables sits between the two — and it has an advantage the other two don't.
A budget by budget lines — labour, subcontracting, equipment, travel — can be read by the finance department. But it doesn't answer the question that matters during the project: is what we have produced worth what we have spent?
The deliverable, on the other hand, is the unit the client bought. It is therefore the only level at which production and spending can be compared. On a property project, the budget per apartment tells you something; the budget per expense item tells you nothing about progress.
Breaking down by deliverables also lets those who know carry the estimate: the project manager estimates in skills — three days of senior developer, two days of acceptance testing — without knowing who will do them; the manager then assigns the actual resources available. Two levels, two owners, one structure.
A project without surprises would be an off-the-shelf product. Since there will be trade-offs, you might as well decide beforehand which ones are possible. Three stances, to be decided at scoping:
This decision determines the revision process. On a fixed-budget project, a drift triggers a scope trade-off; on a fixed-deadline project, it triggers a request for extra funding. Confusing the two means spending three weeks in committee not understanding each other.
The only indicator that gives a timely warning is the estimated cost at completion: the cost of what has been done plus the cost of the estimate to complete. Neither actuals alone, nor the remaining budget, which say nothing as long as you don't know what remains to be produced.
This figure becomes reliable at around 20% completion. At that stage, teams have met the real difficulties, confidence in the estimate rises, and it is time to stabilise the revised budget — before the point of no return, not after.
The budget by deliverable then feeds the billing release: on a fixed-price contract, the value earned on a deliverable is what triggers the billable amount. The same breakdown is therefore used to estimate, steer and invoice.