Prioritising is not about scoring projects. It is deciding which ones go first when you cannot do everything — and writing it down, so that the decision holds until the next quarter.

Project prioritisation means ranking the projects in a portfolio — new requests and projects under way — to decide in which order to deliver them, given the budget and the people available. It produces an ordered list and, above all, a cut-off line: what is above it gets done, what is below it waits.
It is different from the annual project plan. The annual plan sets the scope for the year, once a year. Prioritisation is replayed at every trade-off: a new request, a project going off track, a team losing a skill. It is the same grid, applied more often.
None is better in absolute terms. Each one fits a situation, and most organisations combine two: a quick method for sorting, a finer method for deciding the top of the list.
| Method | Principle | When to use it | Its limit |
|---|---|---|---|
| Weighted scoring | Each project is scored on a few criteria, each criterion has a weight. The score is the weighted sum. | Heterogeneous portfolio, decisions in committee | If the weights are negotiated, so is the result |
| Value / effort matrix | Two axes, four boxes: quick wins, major projects, small projects, projects to drop. | First sort of a long list of requests | Too coarse to separate the top of the list |
| MoSCoW | Must, Should, Could, Won't: essential, important, desirable, not now. | Prioritising the content of a project (work packages, features) rather than a portfolio | Without a rule, everything ends up as Must |
| Cost of delay | What a month's delay on this project costs: lost gain, penalty, risk. | Time-bound gains: regulatory, seasonality, contract | Requires putting a figure on value, which few requesters do |
| WSJF | Weighted Shortest Job First: the cost of delay divided by the size of the project. Small, high-value projects move ahead. | Continuous flow of requests, agile organisations | Relative estimates, hard to defend before a finance committee |
Weighted scoring is the most widely used method in portfolio committees. It works if the grid is built before scoring, not during it.
The cost of each project does not enter the score: it comes in when the ranking is tested against capacity. The estimate remains coarse at this stage — see estimating a project by deliverables.
An IT department has 900 person-days over the half-year, once recurring work has been deducted. Six projects are candidates. The ERP migration is mandatory — end of support for the current version — and uses 300 days: 600 remain to be shared out. The other five are scored with the following weights: value 40%, alignment 25%, urgency 20%, risk control 15% (5 = low risk). Efforts are in person-days.
| Project | Val. | Align. | Urg. | Risk | Score | Days | Cumulative |
|---|---|---|---|---|---|---|---|
| Billing automation | 5 | 3 | 4 | 4 | 4,15 | 120 | 120 |
| Customer portal redesign | 4 | 4 | 3 | 3 | 3,65 | 250 | 370 |
| Financial reporting | 3 | 4 | 3 | 5 | 3,55 | 60 | 430 |
| Field mobile app | 4 | 2 | 3 | 2 | 3,00 | 200 | 630 |
| Data platform | 3 | 5 | 1 | 1 | 2,80 | 350 | 980 |
The first three projects fit within 430 days. The mobile app would take the cumulative total to 630 days, beyond the 600 available: it must be reduced to a first work package of 170 days, postponed to the next half-year, or something else must be dropped. The data platform, well aligned but not urgent and risky, is postponed.
This reasoning in total days is not enough. If billing and the customer portal mobilise the same two developers in the first quarter, the ranking holds on paper and breaks in the capacity plan. The final test is done by skill and by month, not in overall days. It is almost always this test that forces the trade-offs.
Requesters present their projects and propose a score. The PMO prepares the grid, consolidates the scores and calculates the cut-off line. Management control challenges the estimates and the announced gains. The portfolio committee — executive management, finance, business units — decides, and its decision is traced project by project. The roles are worth writing down: see the RACI matrix.
By first taking out the obligations — regulatory, end of support, contract — then applying the same grid to everything else, with a strict ranking. Urgency becomes one criterion among others, with a weight set in advance, instead of being the argument of whoever speaks loudest.
The annual plan decides the scope for the year, once a year, against the budget and capacity. Prioritisation decides the order, and is redone at every trade-off. The annual plan is the result of a first prioritisation; the quarterly reviews are the next ones.
Four or five. With more, the criteria overlap, the scores bunch together and the ranking no longer discriminates. A few well-defined criteria, scored on a written scale, are better than twenty criteria scored by guesswork.
Every quarter for the portfolio, and with every significant new request. A new request never gets in without something in return: if it comes in above the cut-off line, another project drops out, and that is written down.
Yes, on their estimate to complete and on the value still to be gained — not on what has already been spent. Stopping a project halfway is expensive; continuing it when another would bring in more often costs more.
See the Projects and Resources areas, and the IT departments page.
What this article describes is managed in these CESAR.TEAM modules.
Tell us how you manage today: structure, closing rhythm, systems in place. We will prepare a demo on a comparable context.