A RACI matrix is not for describing the organisation: it is for knowing who decides when two people disagree. Badly built, it dilutes responsibility instead of clarifying it.

The RACI matrix crosses a project's activities with the roles that take part in them. In each cell, a letter says how that role is involved in that activity.
| Letter | Role | What it means |
|---|---|---|
| R | Responsible (does the work) | Does the work. There can be several. |
| A | Accountable (approves) | Is accountable for the result and decides in case of disagreement. Only one per activity. |
| C | Consulted (gives input) | Gives an opinion before the decision. Two-way exchange. |
| I | Informed (kept informed) | Is kept up to date afterwards. One-way information. |
The distinction that matters is between R and A. R does; A answers for the result. They can be the same person, but not two different people for the A: that is precisely what the matrix is there to prevent.
Most RACI matrix examples describe product design. Yet the most frequent disagreements are found elsewhere: in the chain that runs from estimate to invoice.
| Activity | Project manager | Team | Manager | Management control | Sponsor |
|---|---|---|---|---|---|
| Estimate the project | R | C | C | C | A |
| Approve the original budget | C | — | I | R | A |
| Plan in skills | R, A | C | C | — | I |
| Assign resources | C | I | R, A | — | — |
| Enter time | I | R | A | I | — |
| Approve time entries | C | — | R, A | I | — |
| Declare the estimate to complete | R, A | C | — | I | I |
| Revise the estimated cost at completion | R | — | C | C | A |
| Decide the billing release | R | — | — | C | A |
Example to adapt: in an IT services company, the billing release often falls to sales management; in an IT department, the sponsor is the business unit that owns the budget. What must not change is the separation between the capacity plan, expressed in skills by the project manager, and the assignment of people, decided by the manager.
The matrix made at launch and never reread. Roles evolve, a sponsor changes, a team is reorganised. A RACI matrix should be reread at least at every change of phase.
The matrix that contradicts the tools. This is the most expensive mistake. If the matrix says the manager approves time but the tool lets the project manager do it, the tool wins. Approval rights must be set up exactly as the matrix describes them, otherwise it remains a scoping document that nobody applies.
Activities without consequences. A matrix that describes twenty communication activities and forgets the budget revision misses what creates conflicts.
Several variants add letters. The most common, RASCI, adds an S for Support: people who help the R without owning the delivery. RACI-VS adds a V for the person who verifies the result and an S for the person who signs off. These variants are useful in highly regulated contexts; for most projects, the original four letters are enough, and a simple matrix is applied more often than a complete one.
See the Resources area for how entry, approval and the capacity plan link together.