The RACI matrix: one A per row, and the rest follows

A RACI matrix is not for describing the organisation: it is for knowing who decides when two people disagree. Badly built, it dilutes responsibility instead of clarifying it.

November 2026· 7 min read· Methods & management
Video call between four members of a project team
Key points
  • R does the work, A is accountable and decides, C is consulted before, I is informed after.
  • One rule before all others: a single A per row. Two As means none.
  • The matrix is only useful if it matches what the tools actually do: who approves time, who revises the budget, who decides to invoice.

Four letters, four levels of involvement

The RACI matrix crosses a project's activities with the roles that take part in them. In each cell, a letter says how that role is involved in that activity.

LetterRoleWhat it means
RResponsible (does the work)Does the work. There can be several.
AAccountable (approves)Is accountable for the result and decides in case of disagreement. Only one per activity.
CConsulted (gives input)Gives an opinion before the decision. Two-way exchange.
IInformed (kept informed)Is kept up to date afterwards. One-way information.

The distinction that matters is between R and A. R does; A answers for the result. They can be the same person, but not two different people for the A: that is precisely what the matrix is there to prevent.

Building the matrix in four steps

  • List the activities and decisions, with a verb: "approve the original budget", "assign resources", not "budget" or "resources". A row that is too broad — "manage the project" — says nothing.
  • List roles, not people. Project manager, team manager, management control, sponsor. Names change; the matrix must survive the first departure.
  • Fill in row by row, starting with the A. If nobody wants to take it, the activity has no owner: that is information in itself.
  • Read it again by column. A column full of Rs signals a bottleneck; an empty column, a role that has nothing to do in the project.

Example: the financial management of a project

Most RACI matrix examples describe product design. Yet the most frequent disagreements are found elsewhere: in the chain that runs from estimate to invoice.

ActivityProject managerTeamManagerManagement controlSponsor
Estimate the projectRCCCA
Approve the original budgetC—IRA
Plan in skillsR, ACC—I
Assign resourcesCIR, A——
Enter timeIRAI—
Approve time entriesC—R, AI—
Declare the estimate to completeR, AC—II
Revise the estimated cost at completionR—CCA
Decide the billing releaseR——CA

Example to adapt: in an IT services company, the billing release often falls to sales management; in an IT department, the sponsor is the business unit that owns the budget. What must not change is the separation between the capacity plan, expressed in skills by the project manager, and the assignment of people, decided by the manager.

The rules that make it useful

  • A single A per row. Two people who "approve together" do not approve: they wait for each other.
  • At least one R per row. An activity that is approved but that nobody carries out stays in limbo.
  • Few Cs. Every consultation costs time. If everyone is consulted on everything, the project moves at the pace of the slowest person.
  • Chosen Is. Too many people informed creates noise; the real recipients end up no longer reading.
  • The A is not the line manager by default. It is the person who has the information and the legitimacy to decide on that specific activity.

Common mistakes

The matrix made at launch and never reread. Roles evolve, a sponsor changes, a team is reorganised. A RACI matrix should be reread at least at every change of phase.

The matrix that contradicts the tools. This is the most expensive mistake. If the matrix says the manager approves time but the tool lets the project manager do it, the tool wins. Approval rights must be set up exactly as the matrix describes them, otherwise it remains a scoping document that nobody applies.

Activities without consequences. A matrix that describes twenty communication activities and forgets the budget revision misses what creates conflicts.

RASCI, RACI-VS: the variants

Several variants add letters. The most common, RASCI, adds an S for Support: people who help the R without owning the delivery. RACI-VS adds a V for the person who verifies the result and an S for the person who signs off. These variants are useful in highly regulated contexts; for most projects, the original four letters are enough, and a simple matrix is applied more often than a complete one.

In CESAR.TEAM

What the platform does
  • The project team's roles and the daily cost of each resource in a single source of truth.
  • Time entered by the team member, then an approval circuit by the manager before the days enter the calculations.
  • The need expressed in skills by the project manager, the assignment of people by the manager.
  • The estimate to complete and the estimated cost at completion owned by the project manager, consolidated for management control.

See the Resources area for how entry, approval and the capacity plan link together.

In the platform

The modules concerned

What this article describes is managed in these CESAR.TEAM modules.

See it in a demo

Let's see what it looks like on your projects

Tell us how you manage today: structure, closing rhythm, systems in place. We will prepare a demo on a comparable context.