Recorded days are the raw material of everything else: actuals, production, margin, the invoice. If that data is wrong or late, everything that flows from it is too.
The most costly confusion in project management control fits in one sentence: euros are compared with days. Three figures coexist on a project, and each has its producer.
The conversion from days to euros is done through the daily cost. As long as that conversion is not explicit and dated, the budget/actuals comparison means nothing — and that is where month-end arguments between operations and finance start.
In practice, it is hard to build a project budget without having planned. The natural order is therefore: capacity plan in skills, then assignment of actual resources, then budget approval. Not the other way round.
Two schools, and the choice is not trivial.
Standard cost per category — junior, experienced, senior, expert, director — protects salary confidentiality, simplifies trade-offs and makes projects comparable with each other. It is the majority choice as soon as a dashboard circulates beyond HR.
Actual cost per individual gives an exact margin, but exposes sensitive information to anyone reading the report. It is reserved for restricted scopes: management control and finance.
In both cases, the daily cost consolidates the loaded salary and a share of indirect costs — premises, workstation, supervision. And it must be historised, with an effective date: without it, a pay rise during the year retroactively rewrites the cost of the whole financial year, and the Y-1 comparison becomes wrong without anyone noticing.
An unapproved time entry is an intention, not data. The minimum workflow has three stages: entry by the employee as they go, approval by the manager, freezing of data at the close. Once frozen, the period is not reopened: corrections go through as adjustments in the following period, traced as such.
This discipline is what makes the data enforceable — with the client being invoiced, the statutory auditor, and the project team itself when a variance has to be explained.
The useful check is monthly and held by line management. Each team leader must be able to see, transparently, what their employees recorded on which projects, and see their absences alongside. A quarterly check centralised in management control always comes too late to correct anything.
Time-entry control is not about tracking down employees. It is about spotting, within the month, the few situations that cost a lot:
These four signals can be read in one view, provided the data is in the same repository as the budget and the schedule. That is the whole point.
The practical consequence: approved time entries directly feed production tracking and billing release. There is no re-keying between time spent and the invoice, so no possible gap between the two.