A finance department does not ask for a project management tool. It asks to know, before the close, what projects are costing and what they will earn.

A finance department's demands on projects almost always come down to the same four figures, kept project by project and consolidated across the portfolio:
The rest — performance indices, earned value, progress ratios — is derived from these four. A finance department that doesn't get them reliably will never ask for a more sophisticated indicator: it will ask for a spreadsheet.
On a project, committed spend goes out very fast. You want to get teams started as early as possible, so you sign subcontracting contracts, order licences, book external resources for three months. The budget is consumed contractually long before it appears in the accounts.
That is where gaps open up, for three reasons that can add up:
Tracking that doesn't distinguish committed from actual mechanically gives too rosy a picture at the start of the project, and too brutal a one at the end.
A finance department's second concern is not cost, it is timing. Between production delivered and amounts invoiced lies WIP: work done, valued, but not yet invoiced — or invoiced and not yet paid.
This WIP has two effects. It weighs on working capital requirements, project by project. And it determines period-end entries: accrued income on what is produced and not invoiced, deferred income on what is invoiced and not produced. These entries are often rebuilt by hand, from a spreadsheet, under deadline pressure.
Continuous reconciliation between production and invoicing removes that rebuilding: entries are derived from data already approved.
The real problem is almost never the quality of the reporting. It is its age. When the real economics of a project are only known at the close, two to three months can easily pass between the moment a project drifts and the moment management finds out. By then, the only possible action is to note it.
Reducing that lag requires data to be produced as you go by those who hold it — the employee for their days, the manager for their assignments, the buyer for their orders — in the same repository. It is an organisational issue before being a tool issue, but no tool can solve it if it isn't designed for it.
A project's return on investment is estimated at launch, rarely measured at the end, and almost always optimistic. Better to accept it: the value of a cost/benefit scoring is not in its accuracy, it is in the fact that it opens the discussion on priorities between projects.
What can really be managed, on the other hand, is the margin per deal: what was invoiced minus what was spent, while the project is under way and you can still act on it.
See the Production & billing domain for the detail of the chain, or the IT services & consulting page for a services-company context.
What this article describes is managed in these CESAR.TEAM modules.
Tell us how you manage today: structure, closing rhythm, systems in place. We will prepare a demo on a comparable context.