The more complex a project, the simpler its dashboard must be. A large project is managed with fewer indicators than a small one, but with indicators that trigger a decision.

A major project is not a project with a big budget. It is a cross-functional project, drawing on resources from several departments, often across several sites and countries. It works like a temporary SME inside the company: its own team, its own budget, its own governance.
A direct consequence for reporting: two levels of reading are needed, a central level and a local level. Rolling out an ERP in ten countries is managed globally on budget and progress, and country by country on workload and acceptance. A single dashboard then serves neither.
On this type of project, the main risk is not measuring badly. It is not seeing enough:
An indicator that triggers no decision has no place in a monthly review. The minimum set, which fits on one page:
| Indicator | What it measures | What it triggers |
|---|---|---|
| Actuals | Recorded days valued + invoices received | Nothing on its own — the basis for the others |
| Committed | Contracts signed and orders placed, not yet invoiced | Cash alert and early overrun warning |
| Estimate to complete | Remaining workload estimated by the project manager | Revision of schedule and assignments |
| Estimated cost at completion | Actuals + estimate to complete | Budget / scope / deadline trade-off |
| Physical progress | Deliverables produced and accepted | Invoicing, contractual milestones |
| Production and margin | Value produced against cost incurred | Decision to continue, renegotiation |
| Plan / actuals variance | Workload drift per deliverable | Lessons learned and re-estimation |
| Utilisation rate | Capacity used per resource | Trade-offs between projects, recruitment |
Two precautions. Physical progress — accepted deliverables — has nothing to do with progress measured in effort: a project may have consumed 70% of its budget and delivered only 30% of its scope. And the project director's confidence level, subjective as it is, remains one of the best leading indicators available. It deserves to be asked every month, and written down.
Indicators are only worth the rhythm that goes with them. Three levels are enough:
Format matters: two summary pages, with access to the detail for those who want to dig deeper. A forty-page report produced every month is not a steering tool, it is an extra production burden for the project team.