It permanently ties up between a quarter and a third of your revenue. The calculation fits in a few lines, and one of its two terms depends only on you.
Working capital is the money you advance to keep the business running before being paid. Project working capital is the same thing applied to a deal: your teams' time, already paid in salaries, whose invoice has not yet been collected.
It appears on no project dashboard. It is read on the balance sheet, and nobody links it to the project that created it.
In a steady state, your working capital expressed in days of revenue equals the average lag between the day produced and the day collected. That lag has two terms, and they add up.
| Term | What it is | Order of magnitude | Who decides |
|---|---|---|---|
| Production → invoice | Time entry, approval, invoicing decision, close, issuing | 30 to 60 days | You |
| Invoice → collection | DSO: the actual payment time of your clients | 65 days on average | Your clients |
| Total | From day produced to day collected | 95 to 125 days | — |
The second term is documented: in 2025, the average payment time of French SMEs and mid-caps stood at 65 days, and worsening, according to the Agicap Data Pulse observatory covering about 8,000 companies. The first, almost nobody measures.
Between 95 and 125 days is 26 to 34% of revenue tied up permanently. For a €10 million company, that is €2.6 to €3.4 million that you finance yourself, continuously.
It is not a loss. It is money that exists, that belongs to you, and that isn't there. The nuance matters, because it changes the nature of the decision: it is not about recovering a lost sum, but about shortening the time during which you are without it.
So the question is not to eliminate this working capital — it is structural. It is to know how much it is, and which of the two terms you can reduce.
On DSO, your levers are contractual and commercial: payment terms, down payments, milestones, reminders. They exist, but they are negotiated client by client and won slowly.
The first term, on the other hand, is entirely internal. And it is not monolithic: it is a chain of four segments, each of which can be measured and shortened separately.
Measure all four over your last three months. Most companies discover that the decisive segment is not the one they thought, and that a whole month is lost between the end of a service and the approval of the corresponding time.
The four segments live in the same chain: time entry as you go with the plan pre-filled, a dated approval workflow, WIP calculated continuously to decide to invoice without waiting for the close, and billing release based on progress rather than on a schedule. The first term gets shorter because nothing waits for the next period.
Before any improvement project, one figure is enough: the average number of days between the end of a service and the issuing of its invoice, on your deals closed over the last twelve months. It is calculated with two dates you already have.
Related to your revenue, it gives you the amount you finance yourself. It is usually the figure that triggers the decision — more surely than a speech about invoicing discipline.
Second article in the series on project management control, after WIP. Accrued and deferred income will follow, then the month-end close.