Construction doesn't need a different project management method. It needs financial steering that can handle what other sectors ignore: interim valuations, change orders, joint contracting and retention.

Updated September 2026· 6 min read· Construction
Key points
  • Invoicing follows measured progress — interim valuations — not a calendar schedule.
  • Change orders account for a large share of the final result and rarely follow the process of the original contract.
  • Retention and payment terms make site working capital a cash issue as much as a margin issue.

Interim valuations

On a construction site, invoicing does not follow a calendar schedule but measured progress: the interim valuation, drawn up at regular intervals, describes what has been done and triggers the corresponding payment.

That changes the nature of steering. The question each month is not “how much have we spent?” but “what is the physical progress of each item, and what can we put in the valuation?”. Three gaps then widen in parallel:

  • between actual progress and the progress put in the valuation;
  • between the valuation submitted and the valuation accepted by the client;
  • between the valuation accepted and its collection.

Each of these three gaps is work produced and not paid. Added together, they make up the site's WIP — and they are managed separately, because they have neither the same causes nor the same remedies.

Change orders

The original contract rarely describes the site as it will be built. Client changes, unforeseen conditions, technical adaptations: additional works pile up, and they carry a significant share of the final result.

The problem is procedural before it is economic. The original contract followed a rigorous process — estimate, approval, signature. The change order, on the other hand, is often born on site, handled verbally, and formalised later. In between, the work is done, the costs incurred, and the negotiating position weakens as time passes.

The management rule that protects the margin: a change order opens a commitment just like the original contract, with its amount, its progress and its link to the site. If it only lives in a letter, it does not exist in steering — and it will only appear in the final account, when nothing is negotiable any more.

Subcontracting and joint contracting

A large share of the site's value is delivered by third parties, under two regimes that must not be confused in financial tracking.

In subcontracting, the main contractor carries the commitment towards the client: the subcontractor's failure remains its problem, and its cost. Subcontractor valuations are reconciled with the corresponding work packages, otherwise you invoice progress you haven't paid for, or the reverse.

In joint contracting, each company in the consortium carries its own work packages. Tracking must then distinguish what belongs to the consortium from what belongs to the company — otherwise the site's revenue is overstated by the co-contractors' share.

Retention and cash

Two mechanisms specific to the sector weigh directly on site cash. Retention ties up a fraction of each valuation until snags are cleared, often a year after handover. Payment terms, for their part, add to the time it takes for valuations to be accepted.

The result: a site can be profitable and consume huge amounts of cash throughout its execution. Working capital is therefore managed site by site, just like margin — and it is anticipated, because a contractor doesn't fail on its margin, it fails on its cash.

In CESAR.TEAM

What the platform does
  • Breakdown into sites and deliverables, with physical progress per item.
  • Commitments tracked from the purchase order, change orders included.
  • Billing release based on measured progress, not on a schedule.
  • WIP calculated continuously: production delivered against amounts invoiced and collected.

See the Construction solution page.

In the platform

The modules concerned

What this article describes is managed in these CESAR.TEAM modules.

See it in a demo

Let's see what it looks like on your projects

Tell us how you manage today: structure, closing rhythm, systems in place. We will prepare a demo on a comparable context.