A capacity plan at 100% in June is wrong in July: holidays have eaten a third of the capacity, and nobody deducted it. Planning is not done once at project start; it is kept up to date, at the pace of what the team can actually do.

Three figures are often confused. Theoretical capacity counts working days. Available time removes absences. Available capacity also removes the time that does not go to projects: management, internal meetings, training, pre-sales.
Only the last one tells you what a team can deliver. Planning on the first means promising days that do not exist.
A team of five people, in July: 21 working days each, once 14 July has been deducted.
| Step | Calculation | Days |
|---|---|---|
| Theoretical capacity | 5 people × 21 days | 105 |
| Absences | Summer leave booked | − 30 |
| Available time | 75 | |
| Non-project time | About 10% | − 7,5 |
| Available capacity | What can actually be assigned | 67,5 |
| Workload planned on projects | 85 | |
| Utilisation rate | 85 ÷ 67.5 | 126% |
The same schedule, read against theoretical capacity, shows 81%: everything seems fine. Read against available capacity, 17.5 days are missing. They are the ones that will make the estimate to complete drift in September.
The exact thresholds depend on the business; what matters is to set them and read them every month, by resource and by team.
A utilisation rate only makes sense if absences and non-project activities are entered where the workload is planned. Is a team member at 60% on projects available for 40%, or on leave? Without absences, there is no way to tell.
The practical rule: everyone enters their leave as soon as it is booked, not the day before they leave. Leave known in May and entered at the end of July has skewed two months of planning.
When the rate goes above 100%, there are only four levers, in this order:
Deciding nothing is also a choice: it leaves the team to make the trade-offs alone, as emergencies arise, and to discover the result in the estimate to complete.
The capacity plan is reviewed every month, before the period, and with every event that changes capacity: leave, an arrival or departure, long-term sick leave, a new priority. A team that rereads it before the summer avoids the September peak.