Resources & capacity

Available capacity and utilisation rate: keeping the plan up to date

A capacity plan at 100% in June is wrong in July: holidays have eaten a third of the capacity, and nobody deducted it. Planning is not done once at project start; it is kept up to date, at the pace of what the team can actually do.

Updated November 2026· 5 min read· Resources & capacity
Team at work in a shared office space
Key points
  • Available capacity is the days actually available: working days, minus absences, minus non-project time.
  • The utilisation rate compares the planned workload with that capacity. Above 100%, the schedule will not hold.
  • It is updated with every event that changes capacity: leave, a new arrival, a departure, a new priority.

Three capacities, only one that counts

Three figures are often confused. Theoretical capacity counts working days. Available time removes absences. Available capacity also removes the time that does not go to projects: management, internal meetings, training, pre-sales.

Only the last one tells you what a team can deliver. Planning on the first means promising days that do not exist.

The calculation, for a summer month

A team of five people, in July: 21 working days each, once 14 July has been deducted.

StepCalculationDays
Theoretical capacity5 people × 21 days105
AbsencesSummer leave booked− 30
Available time75
Non-project timeAbout 10%− 7,5
Available capacityWhat can actually be assigned67,5
Workload planned on projects85
Utilisation rate85 ÷ 67.5126%

The same schedule, read against theoretical capacity, shows 81%: everything seems fine. Read against available capacity, 17.5 days are missing. They are the ones that will make the estimate to complete drift in September.

Reading the utilisation rate

  • Below 85% — headroom, or resources to assign elsewhere.
  • From 85 to 100% — a well-loaded team that can absorb a short-term setback.
  • Above 100% — the schedule does not hold. Trade-offs must be made before the period, not noticed after it.

The exact thresholds depend on the business; what matters is to set them and read them every month, by resource and by team.

Absences and non-project time in the same sheet

A utilisation rate only makes sense if absences and non-project activities are entered where the workload is planned. Is a team member at 60% on projects available for 40%, or on leave? Without absences, there is no way to tell.

The practical rule: everyone enters their leave as soon as it is booked, not the day before they leave. Leave known in May and entered at the end of July has skewed two months of planning.

Making trade-offs when it overflows

When the rate goes above 100%, there are only four levers, in this order:

  1. Postpone a non-critical assignment or milestone.
  2. Reassign part of the workload to a less loaded resource.
  3. Reinforce with a loan from another team or an external partner.
  4. Reduce the scope, by negotiating it.

Deciding nothing is also a choice: it leaves the team to make the trade-offs alone, as emergencies arise, and to discover the result in the estimate to complete.

How often to update

The capacity plan is reviewed every month, before the period, and with every event that changes capacity: leave, an arrival or departure, long-term sick leave, a new priority. A team that rereads it before the summer avoids the September peak.

In CESAR.TEAM

The principles adopted
  • Capacity plan by resource and by team, with the day-by-day workload compared with each person's working pattern.
  • Absences and non-project activities entered in the same schedule, and deducted from capacity.
  • Overload indicator as soon as a day exceeds the working pattern.
  • Generic resources to reserve workload before naming people, then named resources.
In the platform

The modules concerned

What this article describes is managed in these CESAR.TEAM modules.

See it in a demo

Let's see what it looks like on your projects

Tell us how you manage today: structure, closing rhythm, systems in place. We will prepare a demo on a comparable context.